Segment 6: Matheson Avenue to East Craighead Road (March 6, 2023) Design continues for this segment of the Cross Charlotte Trail. The city is coordinating the design of this segment with Norfolk Southern Railroad and other local stakeholders to complete 90% design plans. Real estate acquisition will begin once 90% plans are complete.
Segment 2: Brandywine Road to Tyvola Road (Jan. 30, 2023) Construction continues along the entire alignment of this segment of the Cross Charlotte Trail between Brandywine Road and Tyvola Road. Construction is expected to be complete in the spring of 2023.
Segment 8: North Tryon Street to Orr Road (Jan. 26, 2023) Real estate acquisition continues for this project and the utility relocation phase is expeted to start later this year (2023). During this phase, utility infrastructure, such as underground gas, water and sewer lines, as well as overhead power, telephone and television lines, are moved as needed to make way for construction for the project improvements. The project is expected to be complete in the fall of 2026.
Segment 7: East Craighead Road to North Tryon Street (Dec. 8, 2022) Real estate acquisition is complete and utility relocation has started. During this phase, utility infrastructure, such as underground gas, water and sewer lines, as well as overhead power, telephone and television lines, are moved as needed to make way for construction for the project improvements.
Segment 9: Orr Road to Rocky River Road West (Sept. 9, 2022) Utility relocation continues on this segment and is expected to be complete in the spring of 2023.
Segment 10: Mallard Creek Church Road to Pavilion Boulevard (July 19, 2022) The design is approximately 50% complete. The project team is coordinating with Charlotte Water's sewer project in the vicinity.
Segment 11: Pavilion Boulevard to Kempsford Drive (July 19, 2022) Design is approximately 50% complete. The project team is coordinating with Charlotte Water on the sewer project in the vicinity.