Cross Charlotte Trail

  • Project typeTrails & Paths
  • Project budget$112.9 million for all segments
Two bicyclists wearing helmets riding bikes on the greenway with the Charlotte skyline in the distance

Program Overview

The City of Charlotte is partnering with Mecklenburg County to create a 30+-mile trail and greenway facility that will stretch from the City of Pineville through Center City and on to the UNC Charlotte campus and Cabarrus County line. Once completed, the Cross Charlotte Trail will allow residents to travel seamlessly from one end of Charlotte to the other. Approximately 140,000 residents and 130,000 jobs will be within walking distance of the proposed trail and the adjacent greenways that connect to it.  

Cross Charlotte Trail Segments

There are 11 total segments of the Cross Charlotte Trail, plus a bicycle boulevard that improves connectivity to the trail in North Charlotte.

Checkmark icon - This project is complete Bicycle Boulevard (complete)

Checkmark icon - This project is complete Segment 1: South Charlotte Connector (city portion complete)

Checkmark icon - This project is complete Segment 2: Brandywine Road to Tyvola Road (complete)

Checkmark icon - This project is complete Segment 3: 7th Street to 10th Street (complete)

Checkmark icon - This project is complete Segment 4: Cordelia Park (complete)

Checkmark icon - This project is complete Segment 5: North Davidson Street to Matheson Avenue (complete)

In Progress icon - This project is in progress Segment 6: Matheson Avenue to East Craighead Road (in progress)

In Progress icon - This project is in progress Segment 7: East Craighead Road to North Tryon Street (in progress)

In Progress icon - This project is in progress Segment 8: North Tryon Street to Orr Road (in progress)

In Progress icon - This project is in progress Segment 9: Orr Road to Rocky River Road West (in progress)

In Progress icon - This project is in progress Segment 10: Mallard Creek Church Road to Pavilion Boulevard (in progress)

In Progress icon - This project is in progress Segment 11: Pavilion Boulevard to Kempsford Drive (in progress)

Program Goals

  • To be nationally recognized by putting Charlotte among the top 25 cities in the country with the most multi-use trails
  • To be continuous by closing the gaps between existing trails, thereby creating 26 miles of continuous trail for commuting and exploring as you travel to your desired destination  
  • To be connected by providing a seamless path connecting people to the larger trail network without using a car  
  • To be separated by creating a comfortable trail separating you from vehicle traffic for a safe and enjoyable experience
  • To be convenient by offering transportation choices and convenient access to neighborhoods and businesses across Charlotte  

Map of the Alignment

The map below shows the entire alignment of the trail from the South Carolina state line to Kempsford Drive near the Cabarrus County line. Click on the map to view a larger version. 

a map of Charlotte with the trail shown in solid green showing completed segments and dotted green showing segments not complete yet

Flyover Video of the Brandywine Road to Tyvola Road Segment