Thermal Road Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Thermal Road Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 695 acres, the project will replace aging infrastructure and provide adequate system capacity. The project area is located along Thermal Road between Pineburr Road to the east and Charter Place to the west.

Project Updates

November 2025

Charlotte-Mecklenburg Storm Water Services is working with United of the Carolinas, Inc. to construct storm drainage improvements on Thermal Road. Thank you for your patience.

• A portion of Thermal Road between Ramath Drive and Pineburr Road is anticipated to close on November 17 for approximately 9 months. 

• The first phase of this project includes installation of two large 84-inch and 60-inch storm drainage pipes under Thermal Road.

• Access to residences will be maintained.

• To ensure the safety of motorists, pedestrians and crew, please follow all signs.

            

Estimated Cost: To Be Determined*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Bid

The project is in the bid phase.

Learn more about project phases.


Schedule
Phase Status End Date
Bid In Progress Anticipated November 2025
Construction TBD TBD
Warranty TBD TBD