Pipe Replacement along Old Statesville Rd.
8/20/2025 Update
Charlotte Water (CLTWater) replaced water pipes under Old Statesville Road (Gibbon Road to Pete Brown Road).
Planned Water Outage on Saturday, September 27th at 7:00 pm until 9:00 pm
Who: Businesses on Old Statesville Road (7000-7200 blocks, Gibbon Road to Pete Brown).
Lower Water Pressure, Bubbly or Cloudy Water Possible
Customers on the following streets may experience lower-than-usual water pressure Wednesday night and bubbly or cloudy water once water service is restored.
Who: Berrybrook Lane, Berrybrook Lane, Bufflehead Drive, Cristal Arms Way, Fox Point Drive, Henderson Circle, Henderson Valley Lane, Hopkins Street, Laborde Avenue, Oakburn Drive, Palustris Court, Panglemont Drive, Pete Brown Road, Quinn Drive, Singing Oak Court, Summit Oaks Road and other streets.
If you experience cloudy, discolored water after the outage please:
1. Run cold water from an outside spigot (hose bib) or bath tub for at least fifteen minutes.
2. When water runs clear, run cold water through any faucets where discolored water is present.
3. If water isn’t clear after 20 minutes, call 311 or the contacts on the other side of the page.
7/11/2025 Update
Charlotte Water is installing a temporary pump station to enhance water service to customers. This work is part of a larger effort to optimize the function and resiliency of the area's water system.
What to Expect
- A pump will be delivered Monday, July 14th near the 2500 block of Kelly Road.
-
- Expect a temporary lane closure during delivery.
- The pump is designed to minimize noise.
- Crews will install privacy screening on the temporary fence.
- Throughout the week, crews will install piping (including some above ground) and will test the pipes and pumps.
7/09/24
Crews are installing a new water line along Peachtree Road from Oakdale Road to Ferrell Avenue. Expect to see construction activities through September 2024.
2/27/24
Charlotte Water (CLTWater) completed a Water Transmission Mains Assessment, which identified various improvements and repairs that are needed to optimize the function and resiliency of the existing water transmission system. This work includes repairs and improvements along Oakdale Road, Peachtree Road, Sunset Blvd, and Old Statesville Road. Those traveling in the area can expect:
- Temporary lane closures along Peachtree Road and Oakdale Road as construction progresses.
- Some night work is anticipated to minimize water outage impacts.
- School entrances/exits in the area will remain open for normal access.
- CLTWater reminds those traveling in the area to observe all posted traffic signage and take safety precautions during this time.
08/08/23
- Lakeview Road is now fully open. We thank you for following all posted road detours and closure traffic signs during the construction period.
Project Schedule:
- Traffic Impacts/Detours: July 24 - Sept. 1, 2023
Project Documents:
Old Statesville Rd. Closure / Detour Mailer(PDF, 1MB)
Planned Water Outage Old Statesville Road September 27 2025(PDF, 796KB)
Oakdale Rd., Peachtree Rd. & Ferrell Ave. Impacts (Design)
CLTWater representatives will be working near properties in the area as they conduct field investigations to prepare for construction activities expected to begin Winter ‘23. Residents in the area may see minor clearing activities, as well as survey stakes/flags, paint markings on the ground, and small machinery used for utility locates and geotechnical borings.

Project Schedule:
- Design: May 2023 – November 2023
- Construction: Winter 2023 – Spring 2024
Project Documents:
June 2024 Update(PDF, 106KB)
Zone A Oakdale Ferrell Peachtree Survey Mailer(PDF, 133KB)