Ashe Plantation Neighborhood Wastewater Enhancement Project

  • Project typeWastewater
  • Project budget​To be determined
  • Project phaseCurrent Status: Design

Project Updates

Updates 2026

Project overview

Estimated Schedule:

  • Summer 2026 - Complete design and permitting.
  • Fall 2026 - Crews will deliver heavy equipment, clear easement of bushes and trees. Crews will begin installing pipe.
  • Early 2027 Crews will continue installing pipe in sections.
  • Mid-2027 - Crews will complete testing and restoration.
    • Normal work hours: 7:00 am – 7:00 pm, Monday through Friday.
  • Contractor will work nights and weekends only as needed.

What to expect:

Project goals

  • The goal of this project is to improve service.

Public involvement

Properties that will be directly affected by construction will be contacted to discuss easement agreements. Areas near the construction will be notified before construction.

Project contacts

For information about the force main/pipe project, contact:

Haley Cooke, PE

Project Manager

704-303-1989

Haley.Cook@charlottenc.gov

For information about the pump station at the end of Quarters Lane, contact: 

Justin Webster, PE

Senior Engineering Project Manager

980-312-2768

Justin.Webster@charlottenc.gov