October 2023
Charlotte-Mecklenburg Storm Water Services and Sealand Contractors Corp. continue with construction. Work is anticipated to be complete mid-2025.
Project updates
- Water main improvements have started along Stafford Circle from Emory Lane to Addison Drive.
- Sanitary sewer improvements have started at the intersection of Emory Lane and Stafford Circle.
- Emory Lane at the intersection of Stafford Circle is anticipated to close late November/early December for the installation of two seven-foot box culverts. More information will be provided prior to the road closure.