Sunview/Telfair Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Sunview/Telfair Storm Drainage Improvement Project involves analysis of existing conditions to determine portions of the storm drainage system needing improvement, planning analysis of improvement alternatives, and design and construction of needed improvements. The project is located within a drainage area of approximately 146 acres. The project area is bordered by Archdale Drive to the north, Old Reid Road to the south, Park Road to the east and Old Reid Road to the west.

Project Updates

May 2026

Charlotte-Mecklenburg Storm Water Services is working with LandDesign and their surveyor, CES Group Engineers, LLP, to evaluate the storm drainage system in the Sunview Drive/Telfair Road area. 

Representatives may need to enter your property to collect survey data on the existing system. While state law authorizes access to private property, no building or structure will be entered.

The survey work is scheduled to begin in May and take about two months to complete.

                     

Estimated Cost: To Be Determined*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Design

The project is in the design phase.

Learn more about project phases.