The Summerlin Place Storm Drainage Improvement Project, located within a drainage area of approximately 38 acres, will replace aging infrastructure and provide adequate drainage system capacity. The project is bordered by Wessynton Drive to the south, Summerlin Place to the east and Brynwood Drive to the west.

Project Updates

October 2026

Construction of the Summerlin Place Storm Drainage Improvement Project is complete. Storm Water Services will continue to monitor the project during the next 12 months as part of the warranty phase. The construction inspector will conduct 6- and 11-month inspections during the warranty period. If needed, the contractor will return to the site to make repairs.

Charlotte-Mecklenburg Storm Water Services appreciates your cooperation and patience during the construction phase of this project.

                

Estimated Cost: To Be Determined*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Warranty

warranty-phase.png

 

Learn more about project phases.


Schedule
Phase Status End Date
Bid Completed February 2026
Construction Completed August 2026
Warranty In Progress Anticipated August 2027