Shamrock Gardens Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Shamrock Gardens Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 75 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. The project area is bordered by Purser Drive to the north, Shamrock Drive to the south, Briar Creek to the east and Eastway Drive to the west.

Project Updates

August 2026

Charlotte-Mecklenburg Storm Water Services and Zoladz Construction Company, Inc. continue with construction. Thank you for your patience.

A portion of Finchley Drive between Shamrock Drive and Jennie Linn Drive is anticipated to close on August 31. The road closure is anticipated to last 2 months.

Access to residences will be maintained. To ensure the safety of motorists, pedestrians and crew, please follow all signs. 

              

Estimated Cost: To Be Determined*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Bid

The project is in the bid phase.

 

Learn more about project phases.


Map of Project Area


Schedule
Phase Status End Date
Bid Completed April 2026
Construction In Progress Anticipated
December 2027
Warranty TBD Anticipated
December 2028