Elvis Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Elvis Storm Drainage Improvement Project will reduce street flooding throughout the neighborhood. Located within a drainage area of approximately 1027 acres, the project will replace aging infrastructure and provide adequate drainage system capacity. The project area is bordered by Elvis Drive to the north, McKee Creek to the south, Eastlake Road to the east and Cedarbrook Drive to the west.

Project Updates

May 2025

Charlotte-Mecklenburg Storm Water Services and consultant Hazen & Sawyer have acquired the easements needed for construction. The project team is working on finalizing the design plans. 

The bid phase will begin soon. During this phase, the final plans will be circulated to qualified contractors for a competitive bidding process. Once City Council awards the contract, construction will be scheduled.

         

Estimated Cost: $4,500,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Design

Learn more about project phases.