Solid Waste Services is operating on its regular schedule the week of Veterans Day. Be sure that carts are at the curb no later than 6 a.m. on collection day. It is a green recycling collection week.
The Barrington Storm Drainage Improvement Project will replace aging infrastructure. Located within a drainage area of approximately 42 acres, the project will provide adequate drainage system capacity. The project area is bordered by Somersworth Drive to the north, The Plaza to the south, Craftsbury Drive to the west and McBride Street to the east.
September 2026
Charlotte-Mecklenburg Storm Water Services and engineering consultant HDR, Inc. continue with the design phase.
The project team is coordinating with private utility companies to identify potential conflicts and relocation needs. The project team is working on finalizing the design plans.
*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.
Learn more about project phases.
Storm Water Services
Isiah Glover, PE Project Manager 980-390-7508 Isiah.Glover@charlottenc.gov