May 2026
Construction of the Cedar Street Storm Drainage Improvement Project is complete. Storm Water Services will continue to monitor the project during the next 12 months as part of the warranty phase.
The construction inspector will conduct 6- and 11-month inspections during the warranty period. If needed, the contractor will return to the site to make repairs.
Charlotte-Mecklenburg Storm Water Services appreciates your cooperation and patience during the construction phase of this project.
February 2026
Charlotte-Mecklenburg Storm Water Services and Cinderella Partners Inc., continue with construction. Work is anticipated to be complete early-2026.
• Installation of the box culvert and storm drainage structures continue on Cedar Street.
• Water and sewer relocations are complete.
• Access to businesses in the area will be maintained.
• To ensure the safety of motorists, pedestrians and crew, please follow all signs.
July 2025
New road closure date - July 28.
June 2025
Charlotte-Mecklenburg Storm Water Services is working with Cinderella Partners Inc, to construct storm drainage improvements near 619 South Cedar Street. Thank you for your patience.
- A portion of South Cedar Street between West 1st Street and Stadium View Drive is anticipated to close on July 7 for approximately 8 months.
- Access to businesses in the area will be maintained.
- To ensure the safety of motorists, pedestrians and crew, please follow all signs.