Oct. 2, 2026 - Design phase continues for this project. Real estate acquisition is expected to start in early November. During this phase, the city acquires the property rights needed to build and maintain the improvements identified during the design phase. City real estate agents will contact affected property owners to discuss the acquisition process and answer any questions.
part of the Sidewalk and Pedestrian Safety Program
This project will construct a shared-use path along the north side of West Rocky River Road from Rockland Drive to Old Concord Road. The scope of the project will include 0.8 miles of a new 10-foot-wide concrete shared-use path with certain sections varying in width, an 8-foot-wide planting strip, driveway improvements, wheelchair ramps, concrete curb and gutter, and storm drainage along the north side of West Rocky River Road.
The project team will engage the public through in-person and virtual meetings, as well as project updates and postcards to residents in the project area.
Rendering of a cross-section of the street after project completion. For illustrative purposes only.
Jonathan Hamrick Project Manager Charlotte Department of Transportation 980-219-1785 jonathan.hamrick@charlottenc.gov
To request public meeting materials or other documents, please contact Jonathan Hamrick at jonathan.hamrick@charlottenc.gov.