Oct. 8, 2026 - Real estate acquisition has started for this project. During this phase, the city acquires the property rights needed to build and maintain the improvements. City real estate staff will reach out to affected property owners to explain the city's acquisition process and answer any questions. Construction is expected to start in the fall of 2027.
Part of the Sidewalks & Pedestrian Safety Program
This project will construct a 0.8-mile-long (4,400 linear feet), 12-foot-wide concrete shared-use path along the west side of Old Concord Road from Meadow Vista to Arlyn Circle. The scope includes driveway improvements and new wheelchair ramps.
The project team will engage the public to get resident feedback and share information about the project. Details of upcoming meetings will be shared once they are determined.
Toni Wilson Senior Engineering Project Manager Charlotte Department of Transportation 704-560-6257 toni.wilson@charlottenc.gov