Jan. 26, 2026 - This month, the project reached several major milestones, including receipt of the Certificate of Occupancy and completion of the final commissioning site inspection. The firehouse is fully operational despite a few miscellaneous warranty and electrical items.
City staff and elected officials celebrate the opening of Firehouse 30 on Jan. 6, 2026.
The project team hosted a virtual public meeting on Oct. 4, 2022 to engage and inform residents of the project. View the recording on YouTube.
Groundbreaking: Monday, June 3, 2024 at 3019 Beam Road (view video │view photos)
Uncoupling Celebration: Tuesday, Jan. 6, 2026 at 3019 Beam Road (view livestream │ view photos │ read article on charlottenc.gov)
Christopher Smith Commercial Inspector Mecklenburg County 704-517-8524 christopher.smith@mecklenburgcountync.gov