North Hoskins Rd 601 Storm Drainage Improvement Project

Anticipated Posting Date: 2027-02-15

  • Reference number2027-Q1(Jan-Mar)-CSWS-20354
  • StatusUpcoming
  • SummaryAsset Management performed an inspection of the dual 72-inch CMP beneath N Hoskins Road in May 2024. Several holes with visible soil were observed during the inspection. Severe road settlement was also noted above the culvert.

The City intends to replace 105LF of duel 72in CMP with 105LF of 11inx8in RCBC; add (2) Non-standard headwalls; add 120 LF of 54in RCP; remove 21LF 36in RCP; add (2) DCBs; Add (1) CB; replace approx. 253LF of 12in sewer; replace approx. 120LF 8in Sewer; replace (4) sewer manholes; Add/replace approx. 382LF 2ft6in C&G; asphalt replacement.

Requirements

Insurance Requirements

The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:

  • Automobile-For automobile operations liability
  • Constructions Bonds-For bidding, payment, completion of construction projects
  • General Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injury
  • Workers Compensation-For lost wages and medical expenses of injured workers

Bonding Requirements

The City plans to require the following bond(s) for this solicitation:

  • Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
  • Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
  • Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.

Estimated Total Value

The total project value is anticipated to be:

  • $1,000,000 -4,999,999

Contract Term

The term of the project is anticipated to be:

  • Through Project Completion