Four Mile Creek Rd 9427 Storm Drainage Improvement Project

Anticipated Posting Date: 2026-04-09

  • Reference number2026-Q2(Apr-Jun)-CSWS-19053
  • StatusUpcoming
  • SummaryProject initiated to address a failing 48in CMP culvert. The culvert crosses a high hazard dam with deficiency's that will be addressed by a private HOA. The city intends to install approx. 80LF of 48in RCP and tie into an existing concrete flume; remove and replace approx. 40LF of 15in RCP; add (1) DCB; add (2) CBs; add (1) winged headwall

Requirements

Insurance Requirements

The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:

  • Automobile-For automobile operations liability
  • Constructions Bonds-For bidding, payment, completion of construction projects
  • General Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injury
  • Workers Compensation-For lost wages and medical expenses of injured workers

Bonding Requirements

The City plans to require the following bond(s) for this solicitation:

  • Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
  • Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
  • Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.

Estimated Total Value

The total project value is anticipated to be:

  • $250,000 - 499,999

Contract Term

The term of the project is anticipated to be:

  • Through Project Completion