Collective Q Storm Drainage Improvement Project

Anticipated Posting Date: 2026-10-01

  • Reference number2026-Q2(Apr-Jun)-CSWS-8357
  • StatusUpcoming
  • SummaryThe Project consists of two separate projects, 805 Lynn St. and 3653 Trailer Dr. The proposed plans for the 805 Lynn St. project calls for installation of 308LF of 48" RCP along a new alignment that shifts the system away from the apartment complex.

There is also a 139LF section of 15" RCP to be CIPP lined. 3653 Trailer Dr. aims to realign the existing 24" system to a new outfall point into the stream. The design also requires lining 100LF of 24" CMP with CIPP at the upstream end of the system.

Requirements

Insurance Requirements

The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:

  • Automobile-For automobile operations liability
  • Constructions Bonds-For bidding, payment, completion of construction projects
  • General Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injury
  • Workers Compensation-For lost wages and medical expenses of injured workers

Bonding Requirements

The City plans to require the following bond(s) for this solicitation:

  • Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
  • Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
  • Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.

Estimated Total Value

The total project value is anticipated to be:

  • $1,000,000 -4,999,999

Contract Term

The term of the project is anticipated to be:

  • Through Project Completion