Collective Culverts 1 Storm Drainage Improvement Project

Anticipated Posting Date: 2028-02-11

  • Reference number2028-Q1(Jan-Mar)-CSWS-20401
  • StatusUpcoming
  • SummaryThe Collective Culvert SDIP 1 consists of five separate drainage culverts at the following locations: N Kings Drive (between Elizateth Ave & Armory Dr), Harris

Houston Road (between Astoria Dr & Bridgehampton Dr), Allister Drive (between Elwood Dr & Walnut Wood Dr), Parview Drive (near 4701 Parview Dr N), and Pence Road (between Bandy Dr & Pence Pond Ln).  The improvements will include lining or rehabilitating existing culverts and/or replacing existing culverts.

Requirements

Insurance Requirements

The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:

  • Automobile-For automobile operations liability
  • Constructions Bonds-For bidding, payment, completion of construction projects
  • General Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injury
  • Workers Compensation-For lost wages and medical expenses of injured workers

Bonding Requirements

The City plans to require the following bond(s) for this solicitation:

  • Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
  • Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
  • Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.

Estimated Total Value

The total project value is anticipated to be:

  • $5,000,000 - 9,999,999

Contract Term

The term of the project is anticipated to be:

  • Through Project Completion