Caldwell Williams/Old Plank Storm Drainage Improvement Project

Anticipated Posting Date: 2026-10-26

  • Reference number2026-Q4(Oct-Dec)-CSWS-19059
  • StatusUpcoming
  • SummaryOld Plank portion of project: Project initiated due to failure of 84in CMP system on Old Plank Rd. City plans to remove and replace 86in CMP with 56LF 8'x7' RCBC; Add (2) concrete wingwalls.

Caldwell Williams portion of project: Project initiated due to road flooding. City plans to replace (2) 60in CMP pipes with 39 LF of 13x5 Box culvert. City also intends to add 40LF of 18in RCP; (2) Double catch basins and (2) concrete wingwalls; Pavement and curb replacement.

Requirements

Insurance Requirements

The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:

  • Automobile-For automobile operations liability
  • Constructions Bonds-For bidding, payment, completion of construction projects
  • General Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injury
  • Workers Compensation-For lost wages and medical expenses of injured workers

Bonding Requirements

The City plans to require the following bond(s) for this solicitation:

  • Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
  • Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
  • Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.

Estimated Total Value

The total project value is anticipated to be:

  • $1,000,000 -4,999,999

Contract Term

The term of the project is anticipated to be:

  • Through Project Completion