The Contractor shall provide all labor, supervision, equipment, tools, transportation, miscellaneous materials, permits, inspections, testing, and incidentals required to complete the installation of an Owner-furnished Generator Docking Station at the West Airfield Lighting Vault.
The Lighting Vault is currently equipped with an existing diesel generator without temporary power connections. The docking station must be connected to the existing standby power system ahead of the existing transfer switch.
The work includes, but is not limited to:
- Installation of the owner-furnished generator docking station.
- Construction of the concrete equipment pad.
- Modification of the existing standby power system.
- Installation of new feeders, conduits, grounding, and control wiring.
- Interior lighting upgrades.
- Replacement of exit signs.
- Testing, startup, commissioning, cleanup, and restoration.
Site Visit - See Section 4.0 of the ITB for registration information.
All bidding activity performed through the e-bidding portal found to the right under "Related Information"