April 2024
Project update
• On April 1, Westbourne Drive closed between Balfour Lane and Falconhurst Drive. The closure is anticipated to last five weeks.
• On April 22, the intersection of Westbourne Drive and Falconhurst Drive will be closed. The closure is anticipated to last 30 days.
• Access to residences will be maintained.
• To ensure the safety of motorists, pedestrians and crew, please follow all signs.
• Additional road closures associated with this project are planned for Balfour Lane and Ravenwood Road. Residents directly affected by these closures will be notified in advance as construction progresses in those areas.