Lakeview Road and Reames Road Intersection Improvement (May 10, 2023) - Sidewalk construction between Beatties Ford Road and Rego Street is complete. The contractor is working on the intersection of Lakeview Road and Reames Road. The intersection is scheduled to be closed for approximately three weeks in the summer of 2023. Drivers are encouraged to use extra caution when traveling through the area.
Project construction is scheduled to be completed in the fall of 2023. Landscaping is scheduled for early 2024.
Beatties Ford Road/Sunset Road Pedestrian Improvements, Phase 1 (April 19, 2023) - This project is at final design. Utility markups are being reviewed with the project team's utility team. Once this review is complete, the consultant will submit the design plans for review and signoff by city staff. The project will then enter the bid phase, during which the city uses a competitive bidding process to procure the services of a contractor to build the project. By state law, the construction contract is awarded to the lowest responsible bidder. Construction is expected to start in late 2024.
Peachtree Hills Sidewalk (July 20, 2022) - Fiber optic relocation has been delayed again and is now anticipated to be complete by August 2022. Once that is complete, the city can start construction on the remainder of the Oakdale Road Farm-to-Market Improvements Phase 1 project. This work needs to be complete before the Peachtree Hills sidewalk project team can perform their work. Due to continued material shortages and long lead times, the estimated construction completion of the Oakdale Road FTM project is now anticipated to be mid-2023. Once that work is completed, work can begin on the Peachtree Hills sidewalk project, which is anticipated to be complete by end of 2023. We apologize for this inconvenience and are working diligently to complete the construction in this area. Thank you for your patience.