Water​ Oak Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Water Oak Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 115 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. The project area is bordered by Bertonley Avenue to the north, Addison Drive to the south, Emory Lane to the east and Whitby Lane to the west.

Project Updates

May 2024

Charlotte-Mecklenburg Storm Water Services and Sealand Contractors Corp. continue with construction. Work is anticipated to be complete mid-2025. 

Project updates

  • Planned selective tree removal will begin in the coming weeks in easement areas throughout the project. Then private utility relocations are anticipated to begin.
  • Storm drainage improvements continue along Addison Drive, Stafford Circle, and Emory Lane.
  • Emory Lane at the intersection of Stafford Circle is anticipated to reopen mid-May. 
                

Estimated Cost: $14,100,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Construction

Learn more about project phases.


Map of Project Area


Schedule

Phase
Status
End date
Planning Completed January 2014 
Design Completed  June 2022
Permitting Completed March 2021
Property Easement/Acquisition Completed February 2022
Bid Completed December 2022 
Construction In Progress Mid-2025 
Warranty TBD