CATS Infrastructure Investment Projects

improving your ride, systemwide.

Improving the Safety and Reliability of your Commute

CATS is investing in modern, reliable and resilient infrastructure to ensure our transit system meets the needs of a growing Charlotte region. These improvements help keep buses, rail lines, facilities and equipment in good working order so riders can count on safe and efficient service every day. By maintaining and upgrading the foundations of our transit network, we’re preparing for the future, supporting local mobility and strengthening the communities we serve.

 

Rail

CATS currently operates two rail lines: the Blue Line and the Gold Line Streetcar. The agency operates 42 light rail vehicles and six streetcars, serving 44 stations across 23 miles of rail.

Beginning in 2026 and continuing into 2027, CATS will advance several key projects to maintain and strengthen our rail system. Planned work includes drainage repairs to protect track beds and improve long-term system performance, targeted track repairs to support smoother and more reliable service and enhancements to the overhead catenary system that powers our light rail vehicles. Crews will also complete a DC power system refresh, updating core electrical components that keep trains operating safely and efficiently.

Together, these improvements help ensure the Blue Line and Gold Line continue to serve riders with dependable, high-quality transit.

Scaleybark Drainage Improvements

Work Dates: July 13, 2026, through Aug. 3, 2026

Status: Complete

Customer Impacts: Blue Line trains single tracked between Scaleybark and Archdale stations. Trains initially shared the northbound track between the impacted stations before switching over to the southbound track. This allowed crews to safely complete drainage improvements on both tracks without ceasing Blue Line service.

Project Description: CATS completed drainage improvements at the Blue Line crossing on South Boulevard near Scaleybark Station to protect the long-term stability of the rail corridor.

Prior to this work, stormwater was flowing beneath the rail beds and causing uplift, which had the potential to affect the structural integrity of the line. Crews installed trench drains on both sides of the tracks to move water away from the rail infrastructure and relieve pressure under the track bed.

These upgrades strengthened the reliability of Blue Line operations and improved roadway drainage along South Boulevard, benefiting both transit riders and drivers in the surrounding area.

Rail Power System Upgrades

Work Dates: Aug. 24, 2026, through Jan. 5, 2027

Status: Ongoing

Customer Impacts: No impact to customers.

Project Description: CATS is modernizing the traction power system that supplies electricity to the Blue Line. Each project involves upgrading the DC switchgear inside a traction power substation (TPSS) and replacing the disconnect switches that protect and control high-voltage equipment. Completing both upgrades at the same time reduces labor costs, improves maintenance efficiency and strengthens the reliability of the rail power network.

These TPSS improvements ensure consistent electrical delivery to the Blue Line, supporting safe and dependable rail operations across the corridor.

CATS is completing a total of eight DC Refresh projects systemwide. The overall program is approximately 5% complete.

Gold Line Switch and Signal Upgrades

Work Dates: Oct. 24, 2026, through Oct. 25, 2026

Status: Complete

Customer Impacts: Minimal. The work was completed during the annual Fall 2026 Gold Line outage.

Project Description: During the Fall 2026 Gold Line outage, CATS completed important upgrades to the streetcar’s track-control systems. Crews replaced aging switch machines at the French Street and Sunnyside locations, ensuring the mechanisms that move the streetcar from one track to another continue to operate smoothly and reliably.

The project included upgrading older flush-mounted switch indicator lights to new bar-style signal indicators, which provide clearer and more visible confirmation of switch positions for streetcar operations and maintenance teams.

These improvements strengthen the Gold Line’s switching and signal infrastructure, supporting safe, efficient streetcar movement and long-term system reliability.

Bus Network

CATS currently operates 234 buses, serving 2,852 stops on 61 fixed routes.

Improving bus service is a key part of our systemwide investments. Through the Better Bus initiative, CATS is redesigning routes, increasing frequency on busy corridors and enhancing reliability for daily riders. Visit the Better Bus page to explore these changes in detail.

View CATS Bus Routes and Schedules on the CATS website.

Transit Facilities and Infrastructure

CATS maintains the stations, parking garages, streetscape elements and supporting infrastructure that anchor our transit network across a 629-square-mile service area.

To keep these facilities safe, accessible and operating smoothly, CATS is completing upgrades such as parking garage repairs, station-area improvements, resurfacing work, pavement marking refreshes and targeted civil enhancements at key locations throughout the system.

These investments strengthen the foundations of our bus and rail network and improve the daily experience for riders who rely on our stations, park-and-rides and other transit facilities.

Parking Garage Improvements

Work Dates: June 9, 2026, through Nov. 12, 2026

Status: Ongoing

Customer Impacts: Parking garages will remain available throughout repairs for customers using the Blue Line. Contractors will make small, localized repairs in limited areas of each garage, blocking off a few parking spaces at a time.

Project Description: CATS is completing a systemwide program of repairs and maintenance across several park-and-ride garages to ensure these facilities remain safe, clean and reliable for daily riders. The work includes localized structural repairs, façade restoration, concrete improvements and general upkeep performed in small sections, allowing the garages to remain open throughout construction.

Several garages have already been completed, including JW Clay, University City Boulevard and the South Tryon façade restoration. Work at Sugar Creek has begun, while I-485 and the final phase at South Tryon are scheduled next, with South Tryon expected to wrap up the project on Nov. 12, 2026.

In total, the parking garage improvement program is approximately 54% complete.

These upgrades support long-term facility durability and help maintain secure, well-maintained park-and-ride locations across the CATS network.

South End Station Project

Work Dates: April 2026 through mid-2028

Status: Ongoing

Customer Impacts: There will be several customer impacts over the course of the project, including but not limited to Rail Trail detours, single tracking and bus bridges. Operational changes will be communicated well in advance.

Beginning Monday, Nov. 2, 2026, and ending Friday, Dec. 11, 2026, the Blue Line will single track at various points to support continued construction at the new station in South End.

Trains will single-track between New Bern and Bland stations, alternating between the northbound and southbound tracks. Review the schedule and verify which platform to board the Blue Line.

  • Nov. 2 – 6: Board all trains on southbound (toward I-485/South Blvd Station) platforms between New Bern and Bland stations.
  • Nov. 9 – 13: Board all trains on southbound (toward I-485/South Blvd Station) platforms between New Bern and Bland stations.
  • Nov. 30 – Dec. 4: Board all trains on northbound (toward Uptown/UNC-Charlotte Main Station) platforms between New Bern and Bland stations.
  • Dec. 7 – 11: Board all trains on northbound (toward Uptown/UNC-Charlotte Main Station) platforms between New Bern and Bland stations.

Directional signage will be placed at all impacted stations to guide customers to the correct train access platforms. For any questions, please contact CATS Customer Service by calling 704-336-7433.

Project Description: CATS is advancing a major improvement project in the rapidly growing South End area to expand rail access and strengthen operations along the Blue Line. The project will deliver a new light rail station, a new Rail Trail connection behind Autobell and Cannon Pharmacy and modernized infrastructure that supports long-term Blue Line reliability.

Several key components have already been completed. The new crossover tracks that allow trains to switch tracks were completed in April 2026. The new pedestrian track crossing between Publix and Cortland South End opened on Aug. 31, 2026. The foundation of the station platforms is currently in progress; Blue Line service modifications are in place to support the construction.

Additional work will continue, with significant overhead catenary system upgrades scheduled for January 2027 and station platforms still to be constructed. The new South End Station is expected to open in 2028.

Learn more about the full South End Station project on the main project page.

Platform Improvements

Work Dates: Gold Line: Oct. 24 through 25; Blue Line: Nov. 14 through 15

Status: Ongoing

Customer Impacts: Gold Line platform repairs were completed at French Street and Bruns Street stations during Fall 2026 Gold Line Shutdown. Blue Line platform repairs will require single tracking on Saturday, Nov. 14 and Sunday, Nov. 15.

Beginning Saturday, Nov. 14, 2026, and ending Sunday, Nov. 15, 2026, the Blue Line will single-track to repair spalling concrete at Archdale station. Train will single track between Archdale and Scaleybark station. Customers must board all trains on northbound (toward Uptown/UNC-Charlotte Main Station) platforms between Archdale and Scaleybark stations during this weekend work.

Project Description: In 2026, CATS is completing targeted repairs to concrete surfaces at several stations to maintain safe, durable platform areas for riders.

At the Gold Line’s French Street and Bruns Street stations, sections of the station platforms have experienced concrete degradation and were resurfaced during the Fall 202 Gold Line service outage.

On the Blue Line, Archdale Station is scheduled for spalling concrete repairs for the weekend of Nov. 14 and 15. This work will require single-tracking at Archdale, with trains operating approximately every 30 minutes while repairs are underway.

All platform improvements are planned for weekend construction to minimize impact on weekday travel and will help extend the life of station platforms across the system.

Pavement Marking Upgrades

Work Dates: Oct. 24 through 25

Status: Complete

Customer Impacts: The work was completed over the Gold Line Fall 2026 shutdown.

Project Description: Several intersections along the Gold Line corridor received refreshed pavement markings to improve roadway visibility for drivers. This work will be performed entirely by the Charlotte Department of Transportation (CDOT), which will self-manage both the marking installation and the associated traffic control.

Technology & Mobility Innovations

CATS is modernizing the customer experience across the transit system through upgrades to fare collection technology and other mobility tools.

These improvements include new validator infrastructure at stations along the Blue Line and Gold Line, supporting future fare modernization and more convenient payment options for riders. As these installations move forward across the corridor, they lay the foundation for a more seamless, reliable and user-friendly transit experience.

For additional information on Fare Modernization, please review the project website.

Blue Line Fare Validator Installation

Work Dates: Sept. 28, 2026, through mid-2027

Status: Ongoing

Customer Impacts: No impact to Blue Line service. Platform work will be done in phases, customer access points may be closed. Directional signage will point customers in the right direction.

Please review the current validator installation schedule below.

  • I-485/South Blvd: Sept. 28 – Oct. 2
  • Archdale: Oct. 5 – 9
  • Tyvola: Oct. 12 – 16
  • Sharon Rd West: Oct. 19 – 23
  • Old Concord Rd: Oct. 26 – 30
  • Sugar Creek: Nov. 2 – 6
  • Arrowood: Nov. 9 – 13
  • Woodlawn: Nov. 16 – 20
  • Bland: Nov. 23 – 27
  • 36th St: Nov. 30 – Dec. 4
  • Parkwood: Dec. 7 – 11
  • 9th St: Dec. 14 – 18
  • 7th St: Dec. 21 – 25
  • 25th St: Dec. 28 – Jan. 1

Project Description: CATS is laying the foundation of its Fare Modernization program with the installation of new infrastructure along the Blue Line. This infrastructure will support future fare validators.

The initial installation began at the I-485/South Boulevard Station and represents the start of a systemwide upgrade designed to make fare payment easier and more flexible for riders, creating a more convenient experience across the network.

Work is being completed in short, station-specific phases that keep Blue Line service operating normally while crews install the infrastructure. As installations continue at additional stations, they will help prepare CATS for a modernized, user-friendly fare system.