North Davidson Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The North Davidson Storm Drainage Improvement Project will replace aging storm drainage infrastructure at the intersection of North Davidson Street and East 27th Street. This project includes installation of a large 14-foot-wide box culvert, more than 100 feet long, underneath North Davidson Street.

Project Updates

September 2023

Construction of the North Davidson Storm Drainage Improvement Project is complete. Storm Water Services will continue to monitor the project during the next 12 months as part of the warranty phase. The construction inspector will conduct 6- and 11-month inspections during the warranty period. If needed, the contractor will return to the site to make repairs.

Charlotte-Mecklenburg Storm Water Services appreciates your cooperation and patience during the construction phase of this project.

                      

Estimated Cost: $3,552,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Warranty

Learn more about project phases.


Map of Project Area


Schedule

Phase
Status
End date
Planning Completed February 2019
Design Completed  November 2021
Permitting Completed November 2021
Property Easement/Acquisition Completed August 2021
Bid Completed May 2022
Construction Completed September 2023
Warranty In Progress