Cutchin Drive​ Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Cutchin Drive Storm Drainage Improvement Project will reduce street and structure flooding throughout the neighborhood. Located within a drainage area of approximately 160 acres, the project will replace and/or rehabilitate aging infrastructure and provide adequate drainage system capacity. The project area is bordered by Sharon View Road to the north, Wamath Drive and Mountainbrook Road to the south, McMullen Creek to the east and Sharon Road to the west.

Project Updates

Landerwood Drive and Mountainbrook Road culverts are complete. Street paving on Mountainbrook Road remains. Chaucer Drive storm drainage and sanitary sewer improvements have started. View the May mailer(PDF, 825KB) for more information.

   

Estimated Cost: $10,400,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Construction

Learn more about project phases.


Schedule

Phase
Status
End date
Planning Completed June 2016 
Design Completed March 2021 
Permitting Completed November 2020
Property Easement/Acquisition Completed May 2019
Bid Completed August 2021
Construction In Progress Anticipated Mid 2024
Warranty TBD