Bonwood Storm Drainage Improvement Project

  • Project typeStorm Water Services
Overview

The Bonwood Storm Drainage Improvement Project is providing drainage improvements which include pipe system replacement and rehabilitation. The project is within a drainage area of approximately 124 acres. The project area is bordered by Stonebridge Lane to the north, Andover Road to the south, Sedgewood Circle to the east and Vernon Drive to the west.

Project Updates

October 2023

Construction of the Bonwood Storm Drainage Improvement Project is complete. Storm Water Services will continue to monitor the project during the next 12 months as part of the warranty phase. The construction inspector will conduct 6- and 11-month inspections during the warranty period. If needed, the contractor will return to the site to make repairs.

Charlotte-Mecklenburg Storm Water Services appreciates your cooperation and patience during the construction phase of this project.

      

Estimated Cost: $3,100,000*

*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.


Project Phase: Warranty

Learn more about project phases.


Map of Project Area


Schedule

Phase
Status
End date
Planning Completed April 2020 
Design Completed  July 2022
Permitting Completed August 2022
Property Easement/Acquisition Completed April 2022
Bid Completed March 2023
Construction Completed August 2023
Warranty In Progress