Northeast Water Main Replacement Project

  • Project typeWater
  • Project budget​To be determined
  • Project phaseCurrent Status: Design, Planning

Project Updates

 

Updates 2024

3/22/24
CLTWater will begin construction in the Hampshire Hills area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.
• CLTWater
• RH Price
• Stantec
• Uniforce Construction Corp.
• C & D Utilities
During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The construction schedule for this area is as follows:
Phase II: Winter 2023 - Spring 2024
Phase III: Early Spring 2024 - Summer 2024

CLTW_Hampshire-Hills_PhIIIII_PreConMailer_Graphic_IG.jpg

 

Updates 2023

12/18/23
CLTWater will begin construction in the Shannon Park area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.
• CLTWater
• RH Price
• Stantec
• Uniforce Construction Corp.
• C & D Utilities
During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.
The construction schedule for this area is set for January 2024 to December 2024.

Shannon-Park-Pre-Construction-map-graphic.jpg


09/19/23

CLTWater will begin construction in the Lower NoDa area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.

  • CLTWater
  • RH Price
  • Stantec
  • Uniforce Construction Corp.
  • C & D Utilities

During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The construction schedule for this area is set for October 2023 to January 2024.

CLTW_NE_Lower-NoDa_Pre-Construction_Area2_SocialGraphic_IG.jpg

 


08/18/23

Hampshire Hills

CLTWater will begin construction in the Hampshire Hills area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area:

  • CLTWater
  • RH Price
  • Stantec
  • Uniforce Construction Corp.
  • C & D Utilities

During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The expected construction schedule for this area is September 2023 to March 2024.

CLTW_NE_Hampshire-Hills-Pre-Construction_Mailer_v4_SocialGraphic_IG.jpg


08/03/23

Citiside

CLTWater will begin construction in the Citiside area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.

  • CLTWater
  • RH Price
  • Stantec
  • Uniforce Construction Corp.
  • C & D Utilities

During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The construction schedule for this area is set for Late August 2023 to January 2024.

CLTW_NE_Citiside-Pre-Construction_Social-Map-Graphics.jpg


06/30/23

  • This month, CLTWater will begin conducting field investigations in the Hidden Valley neighborhood. This work is expected to occur on the following 14 streets: Squirrel Hill Rd., Bannister Pl., Mebane Dr., Mt. Kisco Dr., Echo Glen Rd., Rosada Dr., Thornwood Rd., Hughes Dr., Canterwood Dr., Artwin Rd., Massey Ct., Castle Ct., and Kirk Ct.
  • During this time, it may be necessary for authorized representatives working on behalf of CLTWater to access properties to perform surveys, soil borings for geotechnical evaluation, access manholes, and conduct additional investigations. These activities should not inconvenience residents in any way.
  • The Design Phase of the project in the Hidden Valley area is anticipated to be complete in Winter 2024. The Construction Phase will begin after Design and is anticipated to be compete in Summer 2024. 

CLTW_Hidden-ValleyTailgateTalk_Map_Social.jpg


06/21/23

Public Meeting

On Wednesday, June 28, at 5:30 PM the Northeast Water Main Replacement Project team, in coordination with the Hidden Valley Water System Improvements Project Team, will discuss upcoming impacts to the Hidden Valley area. Both teams will be available to address questions from the public.

The public meeting will take place at Northeast Seventh-Day Adventist Church Drummond Fellowship Hall (827 Tom Hunter Road, Charlotte, NC 28213.)


06/13/23

CLTWater will begin construction in the Lower NoDa area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.

• CLTWater
• RH Price
• Stantec
• Uniforce Construction Corp.
• C & D Utilities

During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The construction schedule for this area is set for Summer 2023 to Winter 2024.

Lower-NoDa-Pre-Construction_Map_Graphic


06/16/23

CLTWater will begin construction in the Branch Hill area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.

• CLTWater
• RH Price
• Stantec
• Uniforce Construction Corp.
• C & D Utilities

During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The construction schedule for this area is set for Summer 2023 to Winter 2024.

Branch Hill Pre-Construction Mailer(PDF, 3MB)


06/16/23

CLTWater will begin construction in the University area as part of the Northeast Water Main Replacement Project. During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.

  • CLTWater
  • RH Price
  • Stantec
  • Uniforce Construction Corp.
  • C & D Utilities

During construction, activities such as staging of materials and equipment, pipe installation, and construction traffic will be taking place. Please adhere to posted traffic signage and take safety precautions while traveling in the area. Please note that short, momentary disruptions to service may occur, and if a planned outage is necessary, the project team will notify impacted businesses and residents in advance.

The construction schedule for this area is set for Summer 2023 to Winter 2024.

University Pre-Construction Mailer June 2023(PDF, 3MB)


05/04/23

Charlotte Water is conducting field investigations as part of the Northeast Water Main Replacement Project to ensure ongoing service for customers in the Shamrock Hills project area. This means that representatives may need to access properties in the area to perform surveys and conduct investigations during the investigation and design phase, which is expected to start in Summer 2023. These residents may see minor clearing activities and small machinery used for geotechnical borings, but these activities should not inconvenience residents in any way.

  • The project schedule is as follows:
    • Design Phase - Summer 2023 to Winter 2023
    • Construction Phase - Winter 2023 to Winter 2025

05/04/23

  • Charlotte Water is conducting field investigations as part of the Northeast Water Main Replacement Project to ensure ongoing service for customers in the Shannon Park project area. This means that representatives may need to access properties in the area to perform surveys and conduct investigations during the investigation and design phase, which is expected to start in Summer 2023. These residents may see minor clearing activities and small machinery used for geotechnical borings, but these activities should not inconvenience residents in any way.
  • The project schedule is as follows:
    • Design Phase - Summer 2023 to Fall 2023
    • Construction Phase - Winter 2023 to Winter 2025

05/02/23

  • This month, Charlotte Water (CLTWater) will begin construction activities as part of the Northeast Water Main Improvement Project that will ensure ongoing service for customers in the Shannon Park area.
  • During this time, authorized representatives from the project team (noted below) will be working on or near residential properties in the area.
    • CLTWater
    • RH Price
    • Stantec
    • Uniforce Construction Corp.
    • C&D Utilities
  • The following construction activities will take place in the area:
    • Staging of materials and equipment
    • Pipe installation
    • Construction traffic
      • CLTWater reminds residents to observe traffic signage and take safety precautions while traveling in the area.
    • Short, momentary disruptions of service may occur. If a planned outage is necessary, the project team will notify impacted businesses and residents in advance. 

Project overview

  • Through the analysis of water distribution systems in Charlotte, CLTWater has identified 12 East Charlotte neighborhoods that require water main replacements to better serve residents. The focus of the project is to replace the water mains in the identified areas but also may include other critical repairs discovered during the project.
  • The Design-Build Team has divided the impacted neighborhoods by size and geography into three phases for both Design and Construction.

What To Expect

  • Planning & Design
    • CLTWater will conduct field investigations as part of the Northeast Water Main Replacement Project that will ensure service to the 12 identified East Charlotte neighborhoods.
    • Authorized personnel will be in the neighborhoods working on behalf of CLTWater and will be working on or near residential properties on one or more occasion during the investigation and design phase of the project.
    • During the planning & design period, it may be necessary for representatives to enter upon residential properties to access manholes, perform surveys, perform soil borings for geotechnical evaluation and conduct additional investigations if necessary. These activities should not inconvenience residents in any way.
    • All field crew are instructed to wear identifying clothing (i.e. a companies’ logo) to identify themselves. In addition to personnel, residents may see minor clearing activities in the area, survey stakes/flags, paint markings on the ground, and small machinery used for geotechnical borings. A list of companies involved with this project s included below:
      • RH Price
      • Stantec
      • Stewart Engineering

Project Schedule (Design)

  • Phase I: Summer 2023 – Summer 2025 (Hidden Valley, Branch Hill, Lower Noda)
  • Phase II: Fall 2023 – Fall 2025 (Grove Park, Chestnut Commons, Rosecroft, Oak Forest (North), Hampshire Hills, Citiside
  • Phase III: Winter 2023 – Winter 2025 (Oak Forest (South), Shamrock Hills, Shannon Park

Project goals

  • The goal of the Northeast Water Main Replacement Project is to replace the water mains in the identified 12 neighborhood areas to better serve residents.