Davidson South Street Wastewater Improvements

  • Project typeWastewater
  • Project budget​To be determined

Project Updates

Updates 2023

 09/21/23

  • Charlotte Water (CLTWater) and contractors AECOM (engineering) and Propst (construction) have completed both the design and construction phase of the Davidson South Street Wastewater Improvements Project. In addition to the wastewater work, the project team also replaced an aging force main beginning at Concord Road, running north along Thompson Street. Since Summer 2022, the project team has worked together to install 4,150 feet of pipeline.
  • In the upcoming months, the team will focus on vegetation and stabilization work to ensure the long-term health of the area. Final pavement markings will also be added to promote safety. The team will remove silt fencing and inlet protections that were installed during the construction phase. 

CLTWater_Charlotte_Water_DavidsonSouthStreet_WaterwaterImprovements_Insta.jpg

 


07/18/2023
  • On 7/19, the project team will begin working along Shearer St. The work is expected to last two days and shouldn’t impact traffic or residents in the area. Please observe posted traffic signage and take safety precautions while traveling in the area.

update map of Davidson

 


01/19/2023
  • CLT Water will host a public meeting on Thursday, Jan. 19th at 5:30pm at Ada Jenkins Center in Davidson to share information and answer questions about the Davidson South Street Wastewater Improvement Project.

  • Address:

Ada Jenkins Center

212 Gamble St.

Davidson, NC 28036

  • For those who are unable to join in person, please join us virtually for the meeting at the link below:

This meeting has ended and link is no longer available.

Updates 2022

10/03/2022
  • CLT Water and contractor Propst Construction will input a temporary access road between Cathey Street and Goodrum Street as they continue work on the project. The temporary access road will be in place from Monday, October 3rd through mid – late October.
  • The South Street Phase II closure from Cathey Street to Mimosa Street is expected to remain in place until late October / early November. While the closure is in place, there will be no parking along both sides of Walnut Street from 7am – 5pm. CLTW Goodrum Cathey Road Closure

  • Don't forget to text DAVIDSONPROJECT to 833-358-1988 to sign up for project updates!


08/19/2022
  • CLT Water and contractor, Propst Construction, will close South Street from Cathey Street to Mimosa Street from late August to early October. During this time, there will be no parking along both sides of Walnut Street from 7am – 5pm. Those traveling in the area are advised to observe all posted traffic signage and consider alternate routes.CLTW Davidson Sewer South Street Phase II Closure
  • To receive project updates and traffic impacts, text DAVIDSONPROJECT to 833-358-1988


06/27/2022
  • As part of the Davidson South Street Wastewater Improvement Project, CLT Water and its contractor, Propst Construction, will close a portion of South Street on Monday, June 27th. Spring Street, Old Canal Street and Main Street will be available as detour routes for northbound and southbound travelers on South Street. There will be signage to show drivers the route. This closure is expected to be in place until late August.   See map here(PDF, 426KB).
  • In addition to frequent mailers, residents are encouraged to sign up for text alerts. These alerts will be sent out several times each month and will give residents timely project information on what to expect during a certain timeframe. Those who sign up for alerts are also able to reply with questions they may have for the project team.
  • If interested in signing up for alerts, please text DAVIDSONPROJECT to 833-358-1988.

06/03/2022

Charlotte Water hosted a public meeting on Thursday, May 5, 2022. A recording of the meeting is available on YouTube.


05/03/2022

Charlotte Water will host a public meeting on Thursday, May 5th at 5:30pm to share information and answer questions about the Davidson South Street Wastewater Improvements Project.

The project team has completed the investigation & design phase of the project and expects to move into the construction phase by summer 2022. The project route will begin near the intersection of Hillside Dr. & Lorimer Rd. and will end near Davidson Elementary School. In addition, the project team will replace an aging force main beginning at Concord Rd., running north along Thompson St.

The meeting is open to the public and will start at 5:30pm. Representatives from Charlotte Water and the Design Build team will present an overview of the project, including current work underway and next steps, and they will be available to answer any questions from attendees.

WHAT: Davidson South Street Wastewater Improvements Project Public Meeting

WHEN: Thursday, May 5, 2022 @ 5:30pm

WHERE: Ada Jenkins Center, 212 Gamble St., Davidson, NC 28036

JOIN VIRTUALLY: TBD (will be provided closer to meeting time)

  • Link no longer available
  • Meeting ID: 811 0111 2658
  • Passcode: 313218
  • One tap mobile:
    • +16465588656,,81101112658#,,,,*313218# US (New York)
    • +13017158592,,81101112658#,,,,*313218# US (Washington DC)

Updates 2021

12/20/2021

Charlotte Water is currently in the Investigation and Design phase for the project and expects to move into the construction phase by Summer 2022.

A small number of properties have been identified for a potential easement or temporary construction easement agreement along the proposed project route. An easement agreement allows CLT Water usage of part of a property owner's land after an agreement has been reached. CLT Water representatives will contact all impacted property owners to discuss the easement acquisition process.

Updates 2020

09/21/2020

Charlotte Water is in the design phase of the Davidson South Street Wastewater Improvements project. The design phase is expected to last for approximately 6 months and conclude in early 2021, with a construction timeline to be determined following the conclusion of the design phase.

 

 

Project overview

  • Charlotte Water (CLTWater) is in the design phase for a wastewater project that will ensure ongoing service for our customers in Davidson.
  • The project route begins near the Hillside Dr. and Lorimer Rd. intersection and will end near Davidson Elementary School. 
  • Updates will be posted on this site.

Schedule

  • Design Phase: Complete
  • Construction Phase: Summer 2022 – Fall 2023 

Davidson South Street Wastewater Improvements Project Map

 

Project goals

  • The goal of this project is to use the information gathered from the planning/investigation phase to design necessary wastewater system improvements.

Public involvement

During this period, it may be necessary for Charlotte Water and authorized representatives' personnel to enter upon a limited number of residential properties to access sewer manholes, perform closed-circuit television (CCTV) inspections of the existing wastewater line and conduct additional investigations as may be necessary. Their activities should not inconvenience residents in any way, and ground personnel will provide notification in advance if access to private property is required.

Activities To Expect

During Design Phase:

  • Surveyors
  • Small equipment
  • Flagging & stakes
  • Minor traffic control

During Construction Phase:

  • Staging of materials, large digging equipment & pipe installation
  • Short, momentary disruptions to service may occur, however, we will do our best to notify residents & businesses in the impacted area in advance.
  • Road closures & detours along South St., Lorimer Rd., Hillside Dr. & Cathey St.
  • Paving & site restoration after pipe installation